01 Mill & Overlay approximately 4 miles of US 49 from 28th Street to Creosote Road, known as Federal Aid Project No. STP-0008-01(135) / 107097301 in Harrison County.
1
QandA
1
02 Overlay approximately 4 miles of US 49 SB from Leonard's Mill Creek Bridge North to Simpson County Line, known as Federal Aid Project No. STP-0008-02(104) / 107085301 in Covington County.
1
QandA
1
03 Bridge Maintenance on US 61 at US 82 Bridge Nos. 196.7A & 196.7B, known as Federal Aid Project No. BR-0009-03(052) / 106913301 in Washington County.
Project Completion: 5/31/2016
1
QandA
1
04 Mill and Overlay of US 82 from US 49E to the US 49 Overpass and the frontage roads on the north and south side, known as Federal Aid Project No. STP-0011-02(085) / 107094301 & SFM-0011-02(085) / 107106301 in Leflore County.
Project Completion: 5/26/2016
1
QandA
1
05 Intersection Improvements on US 84 at SR 35, known as Federal Aid Project No. HSIP-0015-02(095) / 106700301 in Covington County.
Project Completion: 6/30/2016
1
QandA
1
06 Overlay approximately 10 miles of SR 27 from Warren County Line to Beechwood, known as Federal Aid Project No. STP-0054-02(026) / 107098301 in Warren County.
QandA
07 Widen and Overlay approximately 8 miles of SR 603 from SR 43 to Dummyline Road, known as Federal Aid Project No. STP-0067-01(008) / 107096301 in Hancock County.
QandA
08 Level & Seal approximately 6 miles of SR 547 from SR 28 to Copiah/ Claiborne County Line & approximately 5 miles of SR 552 at the BOSM to SR 28, known as Federal Aid Project Nos. STP-0306-00(022) / 107099301 & STP-0305-00(016) / 107099302 in Copiah & Jefferson Counties.
1
QandA
1
09 Work necessary for Bridge Maintenance on SR 475 at Hog Creek, known as Federal Aid Project No. BR-7338-00(005) / 106914301 in Rankin County.
Project Completion: 10/28/2015
1
QandA
1
10 Bridge Maintenance on US 11 from Industrial Park to 16th Avenue Bridge No. 101.9, known as Federal Aid Project No. BR-9396-00(012) / 102964302 in Jones County.
Project Completion: 10/9/2015
1
QandA
1
11 Bridge Joint Replacement on SR 63 over Escatawpa River, known as Federal Aid Project No. BR-9999-06(021) / 106918304 in Jackson County.
Project Completion: 10/16/2015
1
QandA
1
12 Bridge Joint Repair in various locations, known as Federal Aid Project Nos. BR-9999-07(011) / 1069183050, 3051, & 3052 in Covington, Lincoln, and Simpson Counties.
1
QandA
1
13 Bridge Replacement on SR 198 over Rocky Creek, known as State Project No. EXB-0028-00(006) / 102488302 in George County.
1
2
QandA
1
2
14 Stream Stabilization and Countermeasures on Bridge No. 49.4 at SR 7 across Potacocowa Creek, known as State Project No. SP-0019-01(008) / 107035301 in Carroll County.
Project Completion: 10/27/2015
QandA
15 Mill & Overlay approximately 4 miles of SR 4 from 1/2 mile North of US 78 to HWY 4 Bypass & approximately 1 mile of SR 7 from HWY 4 to 1/2 miles South of HWY 311, known as State Project Nos. MP-2004-47(004) / 305557301 & MP-2007-47(005) / 305557302 in Marshall County.
Project Completion: 10/29/2015
QandA
16 Mill and Overlay approximately 8 miles of SR 22 from US 49 to SR 463, known as State Project No. MP-5022-45(007) / 305445301 in Madison County.
Project Completion: 10/27/2015
QandA
17 Overlay approximately 2 miles of SR 27 from SR 198 N. to US 98, & approximately 1 mile of SR 583 from SR 27 N. to US 98, known as State Project Nos. MP-7027-74(011) / 305452301 & MP-7583-74(009) / 305452302 in Walthall County.
Project Completion: 11/13/2015
QandA
18 Mill and Overlay approximately 5 miles of US 61 from St. Catherine Creek Bridge in Natchez to St. Catherine Creek Bridge in Washington, known as State Project No. SFM-0009-01(110) / 107042301 in Adams County.
Project Completion: 11/13/2015
1
QandA
1
19 Mill and Overlay approximately 2 miles of SR 315 from Sardis to US 51, known as State Project No. SFM-0017-02 (011) / 107089301 in Panola County.
Project Completion: 11/5/2015
QandA
20 Mill and Overlay approximately 6 miles of SR 12 from SR 15 to the Oktibbeha County Line, known as State Project No. SFM-0018-03(022) / 107049301 in Choctaw County.
Project Completion: 11/13/2015
QandA
21 Overlay approximately 9 miles of SR 26 from East of Pascagoula River Bridge to West of ROW limits of SR 63, known as State Project No. SFM-0028-01(018) / 107077301 in George County.
Project Completion: 11/6/2015
QandA
22 Mill & Overlay approximately 11 miles of SR 25 from SR 483 to SR 16, known as State Project No. SFM-0056-01(090) / 107044301 in Leake County.
1
QandA
1
23 Overlay approximately 6.5 miles of SR 371 from Itawamba County Line to SR 178, known as State Project No. SFM-0071-00(001) / 107050301 in Lee County.
Project Completion: 11/10/2015
QandA
24 Overlay approximately 6 miles of SR 587 between Ervin Reid Circle and SR 184, known as State Project No. SFM-0196-00(004) / 107043301 in Lawrence County.
Project Completion: 11/12/2015
QandA
25 Mill & Overlay approximately 3 miles of SR 345 from South of Center Hill Road to SR 15, known as State Project No. SFM-0857-00(001) / 107048301 in Pontotoc County.
Project Completion: 11/6/2015
QandA
26 Overlay approximately 6.5 miles of SR 348 from Union County Line to US 45, known as State Project No. SFM-0926-00(008) / 107047301 in Lee County.
Project Completion: 11/5/2015
QandA
27 Mill and Overlay approximately 2 miles of SR 182 from Oktibbeha County line to beginning of Concrete Section, known as State Project No. SFM-2709-00(002) / 107046301 in Lowndes County.
Project Completion: 10/30/2015
QandA
28 Install Raised Pavement Markers on various routes in District 1, known as State Project No. SFM-9999-01(005) / 107045301 Districtwide.
Project Completion: 11/24/2015
1
QandA
1
29 Scrub Seal on Various Routes, known as State Project No. SFM-9999-02(006) / 107107301 in Attala County.
Project Completion: 10/23/2015
QandA